FEATURED PROJECTS
East Avenue Street and Storm Drain Improvements
A challenging phase of the project was installation of a 96-inch diameter reinforced concrete pipe under Interstate 15 undercrossing, where excavation of up to 24’ was required for the placement of the pipe – where there was a relatively low vertical clearance between the roadway and the undercrossing. Another challenge was installation of a 96-inch diameter reinforced concrete pipe under Base Line Road which was conducted by pipe-jacking to avoid open cut trenching and to maintain traffic flow on Base Line Road.
Through extensive coordination and partnering with the City of Rancho Cucamonga, City of Fontana, and Caltrans District 8, the contractor completed the project on schedule.
Location: Rancho Cucamonga, CA
Client: City of Rancho Cucamonga
Construction Cost: $14M
Services provided by Aufbau:
- Construction inspection
- Construction management support services